Lower Jhelum Hydroelectric Project
Lower Jhelum Hydroelectric Project is commissioned in 1979. The installed capacity of the power plant is 105 Megawatt. The type of project is Major and its status is Operational. The source of water is from Jhelum River and the basin is Jhelum River. The power station is erected at the North Hydroelectric Region. The owner name of the power plant is Jammu and Kashmir State Power Development Corporation Limited (JKSPDCL) and is under the control of State Government.
The name of Power House of this project is Lower Jhelum Power House. The Hydroelectric Development type of power project is Run of the River Small Pondage and the type of structure is Weir. The type of power house is Surface. The power project is completed in 1979 and soon started its operation after commissioning in the same year itself.
The beneficiary states and union territories of the power plant are Jammu Kashmir, Punjab and Himachal Pradesh. The type of turbine used is Francis. The head class of Turbine is Medium, since it is between 15 and 60 m. There are three turbines in the power plant. The capacity per each turbine is 35 MW. So the total installed capacity is 105 MW. The rated head of power plant has a height of 61 m and the Rated Speed is 214.3 rotations per minute. The manufacturer of both Turbine and Generator of the power plant is by BHEL Bhopal (India).
The Unit sizes of the power plant is 105 Megawatt, i.e., 35 Megawatt x 3 units. The total installed capacity of the power plant is 105 Megawatt. There are three units in operation and all the three units are commissioned with an installed capacity of 35 Megawatt for each units.
How to Reach: The Lower Jhelum Hydroelectric power station is located near to Warikhah in the Baramulla district of Jammu and Kashmir. You can reach this destination via road, rail or air. The nearest well-connected cities and towns are providing bus and auto-taxi services to the power station. The nearest well-connected railway station is Baramulla railway station, which is just 25 kilometer away from power station. There is no airport in the Baramulla district and the nearest international airport is Srinagar Airport.
Project Details:
• Hydroelectric Project Name – Lower Jhelum Hydroelectric Project
• Commission Date – 1979
• Approved Capacity in MW – 105 Megawatt
• Installed Capacity in MW – 105 Megawatt
• Type of Project – Major
• Status – Operational
• Water Source – Jhelum River
• Basin – Jhelum River Basin
• Hydroelectric Region – North HE Region
• Owner – Jammu & Kashmir State Power Development Corporation Limited (JKSPDCL)
• Address – Near Warikhah, Baramulla, Jammu and Kashmir
• District – Baramulla
• State – Jammu and Kashmir
• Contact Number – +91 191 2430548/2439039
• Fax – +91 191 2435403
• Email – jkspdcl@gmail.com
• Website – www.jkspdc.nic.in
• Beneficiary States/ Union Territories – Jammu Kashmir, Punjab and Himachal Pradesh
• Type of Power House – Surface
• Completion of Power Project– 1979
• Turbine Type – Francis
• Turbine Manufacturer – BHEL Bhopal India
• Generator Manufacturer – BHEL Bhopal India
• Unit Sizes – 105 MW (35 MW x 3 units)
• Total Units – 3
• Units Commissioned – All the three units are commissioned