Pathri Power House Bahadrabad Haridwar

Pathri Power House Bahadrabad Haridwar.jpg

Pathri Power House is erected in the Bahadrabad village of Haridwar district in Uttarakhand, India. The power project is commissioned in 1955 with a total installed capacity of 20.4 MW. The type of hydroelectric project is small as its total capacity is less than 25 MW. The type of plant is like a Dam on a canal. The type of power house is Dam Power house. The hydroelectric status of the power plant is Operational. The water source in the process of generation of power is Upper Ganga Canal.

The power house is erected in the Northern Hydroelectric Region of the country. The pathri power house is owned by the State Government and the operating company of the plant is UJVNL. The beneficiary states/districts of the hydroelectric power project are Haridwar and other neighboring districts. The power house is built and completed in 1955. The number of turbines used in the power house is three and capacity of each turbine is 6.8 MW. The type of turbine used in the power house is Kaplan. The maker of turbine of power house is by the J.M. Voith and the maker of generator of power house is by the Siemens. The unit size of power station is 20.4 MW having 3 units of 6.8 MW each. There are three units in operation and all the three units are commissioned.

How to Reach: Pathri Power House is located in the Bahadrabad village of Haridwar district in the Uttarakhand State of India. You can reach this power house via Taxi or Bus from Haridwar. Haridwar Junction railway station is the nearest railway station.

Project Details:

• Hydroelectric Project Name – Pathri Power House Bahadrabad Haridwar

• Commission Date – 1955

• Approved Capacity in MW – 20.4 MW

• Installed Capacity in MW – 20.4 MW

• Type of Project – Small (total capacity less than 25 MW)

• Type of Plant – Dam on a canal

• Configuration of Powerhouse – Dam Powerhouse

• Status – Operational

• Water Source – Upper Ganga Canal

• Hydroelectric Region – Northern Hydroelectric Region

• Owner – Government State

• Operating Company – UJVNL

• Address – Bahadrabad, Haridwar, Uttarakhand, India

• District – Haridwar

• State – Uttarakhand

• Beneficiary States/ Districts – Haridwar and neighboring districts

• Completion of Power Project – 1955

• Number of Turbines – 3

• Capacity per Turbine – 6.8 MW

• Type of Turbine – Kaplan

• Turbine Manufacturer – J.M. Voith

• Generator Manufacturer – Siemens

• Unit Sizes – 20.4 MW (6.8 MW x 3)

• Total Units – 3

• Units Commissioned – All the three units are commissioned