Sanjay Vidyut Pariyojna Hydroelectric Project
The Sanjay Vidyut Pariyojna Hydroelectric Project is located in the Kinnaur district of Himachal Pradesh. It is erected on the river Bhaba, which is an entire underground project with a total installed capacity of 120 Megawatt, containing 3 units each of 40 Megawatt. The exceptionality of this project lies in its underground switchyard. The power project is completed and became operational in the year, 1989- 1990, the evaluated cost was almost INR 167 crores. The whole length of tunnels comprising those secured in after finishing the project is 12 km.
Sanjay Vidyut Pariyojna (Bhabha) Hydroelectric Project is commissioned in 2000. The Approved Capacity of the power plant is 120 MW. The project type is Major, since it is greater than 25 MW. The status of the power plant is completed and are Operational. The source of water is Bhaba River and the river basin is Indus River. The power plant is located in the North Hydroelectric Region of India. The hydroelectric power plant is owned and operated by the Himachal Pradesh State Electricity Board. The beneficiary States of the power plant are Northern states of India. The power project was completed in 1989 and it became operational from the same year itself. The type of turbine used in the power station is Pelton. Bharat Heavy Electricals Limited is the key player in the manufacture of power plant equipment in India. They manufactured the Turbine and Generator of this hydroelectric power plant.
The unit sizes of the power plant is 120 MW. The power plant has three units in operation with an installed capacity of 40 MW for each units. All the units are commissioned.
How to Reach: The Sanjay Pariyojna Hydroelectric power plant is located in the Bhabha river of Kinnaur district of Himachal Pradesh. You can reach this power plant by Bus, train or flight. The regular buses are available from the Kinnaur to the power station. Since there is no railway station in the Kinnaur town, the nearest railway station to Kinnaur is Kalka railway station, which is situated at about 356 km from Kinnaur town. The nearest airport is Dehradun, which is 154 kilometres away from Kinnaur.
Project Details:
• Hydroelectric Project Name – Sanjay Vidyut Pariyojna (Bhabha) Hydroelectric Project
• Commission Date – 2000
• Approved Capacity in MW – 120 MW
• Installed Capacity in MW – 120 MW
• Type of Project – Major (greater than 25 MW)
• Status – Completed and Operational
• Water Source – Bhaba River
• Basin – Indus River
• Hydroelectric Region – North
• Owner – Himachal Pradesh State Electricity Board
• Website - www.hpseb.in
• Address – Kinnaur district, Himachal Pradesh, India
• District – Kinnaur
• State – Himachal Pradesh
• Beneficiary States/ Union Territories – North Indian States
• Completion of Power Project – 1989
• Turbine Type – Pelton
• Turbine Manufacturer – BHEL India
• Generator Manufacturer – BHEL India
• Unit Sizes – 120 MW (3 units x 40 MW)
• Total Units - 3
• Units Commissioned – All the three units are commissioned