Shivpur Hydroelectric Project
Shivpur Hydroelectric Project is commissioned in 1992 with an approved and installed capacity of 18 MW. The type of project is small. Since it has a capacity in between 3 and 25 Megawatt. The status of power plant is completed and are operational. The source of water for the generation of power is from Tungabhadra riverand the basin for the power plant is Krishna. The hydroelectric basin to the power plant is East flowing rivers. The hydroelectric development type of power house is run of the River Small Pondage. The type of Power House is Surface.
The hydroelectric Region is southern hydroelectric region. The power plant is owned by the Karnataka Government and the operating company of the power plant is BPCL. The beneficiary states of the power plant are Karnataka and other South Indian States. The completion of the power project was in 1992. There are two Turbines in Operation and capacity per each turbine is 9 Megawatt. The type of turbine used is Kaplan.
The manufacturer of Turbine is Bharat Heavy Electricals Limited (BHEL) India and also the manufacturer of Generator is Bharat Heavy Electricals Limited (BHEL). There are two units in operation and all the two units are commissioned. The unit sizes of power plant is 18 MW having 2 units of 9 MW each.
How to Reach: Shivpur Hydroelectric Project is located in the Raichur district of Karnataka. You can reach this place via bus, car, train or plane. You will get frequently available transport buses from the raichur town to the power station. Raichur railway station is the nearest place to get frequent trains towards all parts of the country and Hyderabad Airport is the nearest well connected airport providing international as well as domestic air services.
Project Details:
• Hydroelectric Project Name – Shivpur Hydroelectric Project
• Commission Date – 1992
• Approved Capacity in MW – 18 MW
• Installed Capacity in MW – 18 MW
• Type of Project – Small (3 to 25 Megawatt)
• Status – Operational
• Water Source – Tungabhadra
• Basin – Krishna
• Hydroelectric Basin – East Flowing Rivers
• Hydroelectric Region – Southern Hydroelectric Region
• Owner – Karnataka Government
• Operating Company – BPCL
• Address – Raichur, Karnataka
• District – Raichur
• State – Karnataka
• Contact Number –
• Email –
• Website –
• Beneficiary States/ Union Territories – Karnataka and other South Indian States
• Completion of Power Project– 1992
• Number of Turbines – 2
• Capacity per Turbine – 9 MW
• Type of Turbine – Kaplan
• Turbine Manufacturer – Bharat Heavy Electricals Limited (BHEL) India
• Generator Manufacturer –Bharat Heavy Electricals Limited (BHEL) India
• Unit Sizes – 2 units X 9 MW (18 MW)
• Total Units – 2
• Units Commissioned – All the two units are commissioned.